Thursday 17 March 2016

Wee greens renovations

Today we tried out a new way of solid tining & top dressing greens.  We tried out the new process of how we do things   on the wee greens before we carry out the same work to the big greens on Monday 21st March.  Generally in years gone by we would have top dressed after tining but this year we will swap the processes about.  This means we will dress first then tine after, this will stop wheel rutting from the top dresser as the surface tension will be 100% and not be disturbed already.  This also ensure that the holes are open and clean as the weight of the top dresser can close the holes that it runs over.  The wee greens then had a double brush and a feed behind.  This seemed to work well and I'm confident to use the same method on the big greens this coming Monday. 