Saturday 13 November 2010

13/11/10 (construction work)

Generally the construction work is going very well. We have now shaped all bunkers, re levelled the 6th medal tee, installed drains in 1st and 6th green, part filled the ditch on 18 and filled all old bunkers. The bunkers will be finished and turf will be cut in when it becomes dry enough.

New bunkers around the 13th green.




Looking up the 14th fairway, the fairway bunkers have had extra support added to there backs.




New greenside bunkers at the 14th green.




New greenside bunker on LHS of green and bunker on RHS has been reshaped.




Reshaped bunkers at 16th greenside.





Bunkers on 17th greenside have been reshaped.




Ditch on 18 has been filled on LHS and has been opened up on RHS.





New greenside bunker on LHS of 18th green.




New RHS greenside bunkers on 18th green.