We are getting though the dozer work now. The carry at the new 16th has had the soil reapplied. The big job is the new 6th fairway, this has really taken shape and weather dependant hopefully will be all soiled up by the weekend.
Wednesday, 19 March 2014
general course work
The greens have been pedestrian cut again this week. We have been cutting them once a week for the last few weeks.
We have also given the tees and approaches there first cut.
Saturday, 15 March 2014
Dozer
Bill Geddes has been in today and finished all the 360 digger work that was needing done with the tilting bucket (old pond at the old 17th, tee carry @ 18 and finishing the 5th tees.
The bull dozer also arrived this morning and will re commence work on the 16th carry and old 8th fairway tomorrow morning.
Thursday, 13 March 2014
Wednesday, 12 March 2014
Soiling up
The 17th green has been final soiled and is getting fine rake and prep.
We have now moved onto the new 14th green and by end of play Thursday I would hope to have this soiled up.
The old 8th fairway, work will re commence over the weekend (weather permitting) the D6 bulldozer coming in to begin soiling up.
Monday, 10 March 2014
Top soil
The weather had finally improved enough to begin top soiling the new areas. We have started on the new 17th green surround. By the end off the day we had over half off the surround soiled up. This is the bigger green surround out off the 2.